The sequence below explains the method. Pattern design, process settings, finishing and inspection are defined for each project.
01Review the drawing
Identify the material grade, casting geometry, functional surfaces and required delivery condition. Review wall transitions, allowances and features that may need machining.
Confirm: drawing revision, quantity, critical dimensions and acceptance requirements.
02Prepare the foam pattern
Create the expendable pattern and assemble it with the gating arrangement. Pattern geometry and assembly influence the shape that the molten metal will reproduce.
Review: dimensional stability, pattern condition, joints and handling.
03Coat & support the pattern
Apply a permeable refractory coating and dry it before placing the pattern in a flask. Loose, unbonded sand is filled around the pattern and compacted by vibration.
Review: coating coverage, drying condition and sand support around the geometry.
04Pour & allow to solidify
Molten metal enters the mold, decomposes the foam and takes its place. The casting is allowed to solidify and cool before it is removed from the surrounding sand.
Review: material, mold filling, gas removal and the cooling sequence.
05Finish & inspect
Remove gates and remaining coating, then carry out the agreed finishing operations. Machining, treatment and inspection are included where specified in the project scope.
Confirm: final dimensions, surface condition, required records and packing.